Published project · Facilities

Use less energy across campus cooling plants

How the University of Melbourne improved cooling plant performance using its existing controls.

Project by Exergenics and the university’s controls contractor

Exergenics’ University of Melbourne case study
The problem
The university’s chilled-water plants served buildings with very different loads. A research facility and a teaching building could not use the same operating settings.
What changed
Exergenics used each building’s operating data to recommend when chillers should start and stop. The existing contractor implemented those changes in the building controls.
What happened
Exergenics reports 426 MWh in annual savings across the nine buildings with a full year of measurement.

A related project I can help with

Connect building alarms to maintenance so a recurring fault becomes one job with the evidence attached. Check the original fault again after the repair.

Related technical design

The operating problem

A campus can have a functioning BMS in every building and still operate its chillers inefficiently. A teaching building has timetable peaks, a research building carries an overnight load, and replacement equipment may run against a sequence written for retired plant. Portfolio energy totals hide which combination of chillers, pumps and towers served a given load.

Scope of this study

A supported building management system (BMS) provides commanded and proved states. Meters provide the energy baseline. Local controllers run the equipment. The facilities team records overrides and maintenance.

Proposed architecture

Build a per-plant point register from controls drawings, meters, equipment schedules and BMS trends. Validate units, intervals and sensor plausibility with the controls contractor. Confirm the installed product’s BACnet PICS, point access, priorities, supported services and permission to export. Facilities receives monitoring and operating comparisons. Existing controllers retain interlocks and manual operation.

Campus chilled-water operations

Follow the data, then the authority.

The upper route carries observations and advisory evidence. The local controller remains a separate authority with witnessed change and manual control.

A supervisory evidence path from BMS trends through meter checks to an advisory station, with a separate local interlock assembly.
Campus chilled-water operationsIllustrative interaction · synthetic data
Run an example eventSynthetic data · local replay
  1. 11:20 · sampleInput

    The facility trend shows a stale reading from flow point FM-13.

  2. 11:21 · sampleDecision

    The quality rule excludes the point from the operating comparison.

  3. 11:21 · sampleOutcome

    The workflow creates an advisory item. The existing local sequence continues.

  4. 11:33 · sampleRecovery

    The operator and controls contractor validate the point identity and instrument before reinstating comparisons.

Trend data becomes an operating comparison

Read approved plant points and metering. Check timestamps, units and calibration before an operator sees how the plant performed under comparable loads.

BMS trends

Read agreed temperature, flow and run-state trends from the BMS.

Owner
Building controls owner
Example input
Point identifiers, engineering units and timestamped observations
Example output
Approved read-only trend series
Operating constraint
Verify product capabilities, permissions and point mapping before using the feed.
Comparison

Join valid metering and BMS data to compare performance at similar loads.

Owner
Energy manager with facilities engineering
Example input
Meter intervals, point quality and outside-air conditions
Example output
Operating comparison qualified by data coverage and load
Operating constraint
Reject stale values and account for weather and load. A single comparison cannot establish energy savings.
Local controls

Maintain safe local sequence, interlock and manual operations.

Owner
Qualified controls engineer and site operators
Example input
Site-approved sequence, field safeties and local override
Example output
Local equipment state and witnessed control changes, where separately authorised
Operating constraint
Supervisory inputs are observational. Controls changes require a separately approved design, commissioning and rollback.
Operator advisory

Show the operator evidence and a recommended next investigation.

Owner
Facilities operations lead
Example input
Validated comparison and plant context
Example output
Advisory item with an accountable operator
Operating constraint
Operator review precedes any change. The advisory is not a plant command.
Point validation

Investigate the point mapping, measurement and stale data before restoring the comparison.

Owner
Facilities operator and controls contractor
Example input
Stale flow signal FM-13 and the affected time range
Example output
Validated sensor or a documented gap
Operating constraint
Do not fill an unreliable sensor with a default that appears to be a real reading.
Systems and interface assumptions
System categoryRecord and identifierProposed interfaceAuthoritative ownerDependency to confirm
BMSSite, plant, point and trend identifiersRead selected points through an approved interfaceBuilding controls ownerPoint list, PICS, priority, write restrictions and export permissions
MeteringMeter ID, interval and engineering unitRead authorised trend or metering exportEnergy managerCalibration, clock alignment and valid loads
Facilities workflowRecommendation, override and change ticketWrite an advisory work item if approvedFacilities operatorDecision owner and operator override procedure
Local controlsEquipment interlocks and active sequenceQualified controls contractor onlyControls engineerLocal manual mode, witnessed commissioning and rollback
Event sequence Select a step for details
  1. Source recordsMetered load, equipment status and BMS trends
  2. ProcessingMap trends, validate sensors and prepare operating comparisons
  3. Decision ownerControls engineer and facilities operator assess the recommendation
  4. Operational outputReviewed advisory evidence and an agreed measurement plan

From recurring fault to verified repair

Suppose the chilled-water valve is commanded closed during an unoccupied period but the flow meter still shows flow. Review the controller mode, override history and meter quality first. A stale meter reading, a frost-protection mode or an active commissioning override can make that evidence unusable. Repeated readings on the same equipment belong to one investigation during the agreed observation window.

A facilities operator can raise a maintenance work order from the investigation with the affected asset, timestamps, trend and operating mode attached. If a technician clears the job, check the original condition again in a comparable operating period. If flow persists, reopen the investigation with the new trend. Facilities and the controls contractor agree who reviews the reopened item and who can change the sequence.

External project reference

Exergenics reports optimisation across fourteen University of Melbourne plants. For nine with a full year of measurement and verification, it reports 426 MWh in annual savings and an average measured saving of 11.1%. The figures describe Exergenics’ project. Any buyer assessment requires its own meter boundary and weather- and load-adjusted baseline.

From individual buildings to an operating portfolio

Start with one well-metered plant and a controls contractor who can access the current sequence. Review measured results with facilities and the energy manager. For the next building, reuse naming conventions, monitoring and acceptance tests, while re-identifying equipment, control authority and local conditions. A research lab and a lecture hall must not inherit one another’s operating limits.

Reliability and operating controls

A failed flow meter, maintenance event or active override invalidates relevant comparisons. Mark the evidence stale and route an advisory item to facilities. The controls engineer owns any sequence change, commissioned fallback and local manual control.

Illustrative operating scenario

During a teaching break, one building’s load falls while a research wing remains occupied. The shared plant is running an equipment combination tuned for the normal timetable. The controls team compares feasible combinations against the observed load, tests the approved sequence and verifies that the research spaces stayed within their site-defined requirements.

Delivery boundaries

The integration scope covers mapping, data quality, monitoring, change evidence and analysis. The client’s qualified controls engineer owns sequence changes, equipment protection, interlocks and witnessed commissioning. The energy manager owns the measurement boundary.

Expected business impact

Facilities could identify which plants run inefficiently under comparable conditions and decide where a controls change is justified. Track cooling service, plant availability and measured energy together.

Acceptance test and handover

Define the meter boundary with the energy manager. Compare plant input energy with cooling delivered under comparable weather, loads and occupancy. Keep maintenance periods, equipment changes and overrides visible. Set service criteria and an agreed baseline before claiming savings.

Test point identity and freshness, sensor quality, engineering units, missing intervals and the ability to keep operating on loss of supervisory data. If the controls engineer commissions a change, agree weather- and load-adjusted measurement, service constraints and period exclusions before assessing energy performance.

Industry context and design references

Exergenics · University of Melbourne chilled-water optimisation

The University of Iowa used building analytics to identify faults and route them into a facilities response process. US Department of Energy · University of Iowa building analytics case study

CSIRO · Chiller optimisation research and application

Australian Government · Building management systems for HVAC

A PICS identifies vendor-declared capabilities for a specific product. Site permissions remain a separate check. BACnet International · Protocol Implementation Conformance Statement

Discuss a similar project All case studies