Give hospital maintenance a usable asset register on day one

How a new hospital carried equipment records from construction into maintenance.

Project by The hospital’s construction and commissioning team

Autodesk’s Arkansas Children’s Hospital case study
The problem
The facilities team needed reliable equipment information as soon as the new hospital opened. Construction and commissioning teams were collecting that information in several tools.
What changed
The project team captured equipment data during construction and published it into a shared environment. The hospital carried those records into its maintenance software.
What happened
Autodesk reports that more than 2,700 asset records were in the system when the hospital opened, with preventive maintenance already running.

A related project I can help with

Agree on asset IDs and required records before handover. Send incomplete or unaccepted equipment back for review before creating maintenance schedules.

Related technical design

The operating problem

A fire and mechanical services contractor hands over a commercial building in stages. Commissioning certificates are attached to the project record, the asset list is exported separately, and the maintenance coordinator needs serviceable equipment in the job system before the first visit. A last-minute equipment substitution or a plantroom renamed in the drawings can leave the right certificate attached to the wrong asset. A project-level completion flag can also hide an unsigned asset in a stage the service team is already being asked to take over.

Scope of this study

Responsible trades hold commissioning evidence. A project record identifies installed plant. The facilities platform owns the maintenance register and work schedule.

Proposed architecture

Begin with one completed stage and one asset class. Map each project asset tag to the maintenance asset ID using the site, stage and verified physical location. Carry over the installed model, serial number when available, the current commissioning evidence and its revision, handover status and service-contract reference. Link to the approved schedule and service basis. Have the service owner confirm the first due window before creating planned work in the maintenance platform. Use native imports and APIs for data the two systems can already exchange.

System responsibilities and interfaces
  1. Project recordsInstall evidence and equipment ID
  2. Asset mappingTranslate handover into site register
  3. Facilities + specialistConfirm identity and authorised scope
  4. Maintenance systemAccepted asset and first service instruction
Systems and interface assumptions
System categoryRecord and identifierProposed interfaceAuthoritative ownerDependency to confirm
Project platformSite, stage, physical tag and certificate revisionRead register and evidence referencesCommissioning leadCertificate history, replaced assets and evidence access
Staging registerAsset match, approved scope and acceptanceWrite approved crosswalk and unresolved evidenceService managerApproved schedule basis and access responsibilities
Maintenance systemMaintainable asset ID and initial work orderImport accepted asset and approved first visitService coordinatorExisting assets, deduplication and confirmed first-visit owner
Event sequence Select a step for details
  1. Source recordsInstalled asset register, commissioning evidence and maintenance contract scope
  2. ProcessingMatch asset identity, validate revisions and flag missing service inputs
  3. Decision ownerCommissioning lead corrects evidence and service owner accepts the asset
  4. Operational outputMaintenance system receives approved asset records and first service work

What moves between project and service systems

The project platform keeps commissioning evidence and its revision history. The service platform owns maintenance assets, technicians and work orders. A staging register carries the matching key, the shared fields, who accepted them and the linked evidence. It also records imports and follow-up to support reconciliation when sites are handled in different stages.

If the service team already has a site asset register, match against it before creating anything new. Confirm floor, plantroom and access instructions with the site contact. Keep asset class and contract coverage distinct so a warranty check is assigned to the right person before dispatch.

Where people intervene

Flag an unsigned commissioning sheet, conflicting asset tag, missing service scope or proposed date outside an approved access window. The responsible person decides what evidence is needed and can annotate an accepted exception. Existing compliance and service obligations stay with the teams that approve them.

For a multi-site rollout, agree a shared asset data template and site-level variations. Put import access, queue ownership and failed-job notifications in the handover so a new site can use the same controls after delivery.

Reliability and operating controls

Use a staging register with submitted, correction required, accepted and scheduled states. Retain superseded certificates and replaced asset IDs. The competent specialist records the approved maintenance schedule basis since text extracted from a document cannot establish obligations. The service manager accepts the current record, access constraints and the first-visit owner.

Illustrative operating scenario

During a staged handover, the maintenance sheet shows the design model for an air-handling unit. The installer fitted a different model and uploaded the updated test record. The record stays in review while the supervisor confirms the physical tag and replaces the outdated schedule entry. The service coordinator accepts the updated record and the contract-approved service window. The integration creates one planned visit, even when the corrected asset file is sent twice.

Delivery boundaries

The design covers evidence mapping and software handover. Only the relevant licensed or competent people assess certifications, make safety decisions and approve the maintenance regime.

Expected business impact

Facilities could see which assets are ready for service and which lack usable evidence. Test rejected handovers, duplicate equipment records and time to create the first approved work order.

Acceptance test and handover

Compare a previous handover with the same asset class in a current stage. Count duplicate assets, missing or superseded documents, records accepted on the first submission, time spent preparing the service schedule and approved assets without a confirmed first visit. On rollout, verify that every planned job points to the correct asset, scope and approved timing. Track recurring rework by site or contractor to distinguish bad source data from mapping errors.

Reconcile the accepted staging register against the maintenance import. Test a split-stage handover, duplicate import, late certificate, substituted unit and changed access window. Provide the coordinator with an exception list, the source-evidence link, the import and rollback procedure, and a weekly check for accepted assets with no upcoming job. Retain approval records under the organisation’s access and retention policies.

Industry context and design references

Victorian School Building Authority · Building handover and commissioning

Country Fire Authority · Essential safety measures for businesses

Autodesk · D&E Air Conditioning project asset and commissioning workflow

Discuss a similar project All case studies